Public Procurement & Statutory Audit Tracker

Where Does India's Money Go? — Public Spending & Procurement Tracker

Tracing public tax funds from Union Budget Demands for Grants → Central Public Procurement Portal (CPPP) contract awards → Corporate EPC contractors → Physical delivery milestones → Statutory Comptroller & Auditor General (CAG) audit observations.

Public Procurement & Statutory Audit Integrity Protocol

Tracing tax rupees end-to-end: from Union Budget Demands for Grants to Central Public Procurement Portal (CPPP) contract awards, EPC contractors, physical delivery milestones, and statutory Comptroller & Auditor General (CAG) compliance reports.

TOTAL SANCTIONED CAPEX
₹3.89 Lakh Cr
10 Mega National Corridor Projects
TRACKED CPPP / GeM AWARDS
₹56.4 Thousand Cr
Verified EPC & Viaduct Contracts
AVG PHYSICAL PROGRESS
78.5% Completed
MoSPI IPMD Monitored Corridors
CAG AUDIT DEFICIENCIES TRACKED
₹26.7 Thousand Cr
Statutory Audit Quantified Variances
Sector:
Status:
RailwaysState: GJDelayed (36 mo)

Mumbai–Ahmedabad High Speed Rail (Bullet Train)

National High Speed Rail Corporation

Physical Progress:48%
Completed: 244 kmTarget: 508 km
SANCTIONED COST₹108,000 Cr
REVISED COST₹115,000 Cr
DISBURSED OUTLAY₹54,200 Cr
Cost Variation:+₹7,000 Cr (+6.5%)
Target: 2027-12-31
Roads & HighwaysState: DLDelayed (18 mo)

Delhi–Mumbai Expressway (Phase 1 & 2)

Bharatmala Pariyojana

Physical Progress:84.5%
Completed: 1171 kmTarget: 1386 km
SANCTIONED COST₹98,234 Cr
REVISED COST₹104,500 Cr
DISBURSED OUTLAY₹88,200 Cr
Cost Variation:+₹6,266 Cr (+6.4%)
Target: 2025-12-31
RailwaysState: MHDelayed (30 mo)

Western Dedicated Freight Corridor (Dadri–JNPT)

Dedicated Freight Corridors (DFCCIL)

Physical Progress:91%
Completed: 1370 kmTarget: 1504 km
SANCTIONED COST₹51,100 Cr
REVISED COST₹58,400 Cr
DISBURSED OUTLAY₹52,100 Cr
Cost Variation:+₹7,300 Cr (+14.3%)
Target: 2025-06-30
RailwaysState: UPCOMPLETED

Eastern Dedicated Freight Corridor (Ludhiana–Dankuni)

Dedicated Freight Corridors (DFCCIL)

Physical Progress:98%
Completed: 1337 kmTarget: 1337 km
SANCTIONED COST₹30,358 Cr
REVISED COST₹32,100 Cr
DISBURSED OUTLAY₹31,800 Cr
Cost Variation:+₹1,742 Cr (+5.7%)
Target: 2024-03-31
Roads & HighwaysState: RJON_SCHEDULE

Amritsar–Jamnagar Economic Corridor

Bharatmala Pariyojana

Physical Progress:86.5%
Completed: 1058 kmTarget: 1224 km
SANCTIONED COST₹30,000 Cr
REVISED COST₹31,800 Cr
DISBURSED OUTLAY₹27,500 Cr
Cost Variation:+₹1,800 Cr (+6.0%)
Target: 2025-09-30
RailwaysState: DLON_SCHEDULE

Vande Bharat Trainsets Procurement (200 Rakes)

Rolling Stock Modernisation

Physical Progress:55%
Completed: 110 kmTarget: 200 km
SANCTIONED COST₹26,000 Cr
REVISED COST₹26,000 Cr
DISBURSED OUTLAY₹14,200 Cr
Cost Variation:On Budget (0.0%)
Target: 2026-03-31
Roads & HighwaysState: KAON_SCHEDULE

Bengaluru–Chennai Expressway (NE-7)

Bharatmala Pariyojana

Physical Progress:88%
Completed: 230.5 kmTarget: 262 km
SANCTIONED COST₹17,930 Cr
REVISED COST₹19,200 Cr
DISBURSED OUTLAY₹16,800 Cr
Cost Variation:+₹1,270 Cr (+7.1%)
Target: 2025-06-30
Roads & HighwaysState: UTDelayed (20 mo)

Char Dham Mahamarg Vikas Pariyojana

All-Weather Himalayan Highway

Physical Progress:82%
Completed: 729 kmTarget: 889 km
SANCTIONED COST₹12,070 Cr
REVISED COST₹13,400 Cr
DISBURSED OUTLAY₹10,900 Cr
Cost Variation:+₹1,330 Cr (+11.0%)
Target: 2025-10-31
Roads & HighwaysState: HRCOMPLETED

Dwarka Expressway (NH-248BB, Urban Extension)

National Capital Region Network

Physical Progress:96.5%
Completed: 28 kmTarget: 29 km
SANCTIONED COST₹9,000 Cr
REVISED COST₹10,200 Cr
DISBURSED OUTLAY₹9,850 Cr
Cost Variation:+₹1,200 Cr (+13.3%)
Target: 2024-03-31
Roads & HighwaysState: JKDelayed (24 mo)

Zojila Tunnel & Approaches (NH-1)

Strategic Border Infrastructure

Physical Progress:56%
Completed: 7.9 kmTarget: 14.15 km
SANCTIONED COST₹6,800 Cr
REVISED COST₹7,550 Cr
DISBURSED OUTLAY₹4,200 Cr
Cost Variation:+₹750 Cr (+11.0%)
Target: 2026-11-30